Can a business stay open while its roof is torn off? Yes, if the roof work is planned around the business instead of the other way around. On this Walgreens, a shingled mansard wrapped around a flat roof held down by tons of rock, and the store kept filling prescriptions the whole time. Here's how the job was sequenced, and what any building owner should ask before a commercial reroof.
The short version
- A roof replacement on an open business is mostly a planning problem: what happens on which day, and where people walk.
- This flat roof wasn't glued or screwed down. It was held in place by rock ballast, which had to be vacuumed off before anything else could start.
- A dedicated loading day (materials up, safety gear set, temporary fencing in place) keeps tear-off day short and tidy.
- The whole project was planned for about 4 days so the pharmacy never had to close.
What made this roof tricky?
Two roofs in one. Shingles wrapped around the outside of the building, and a flat roof sat in the middle. In the video we called it a project that would “take a lot of our resources,” and the reason was what was holding that flat roof down.
By our estimate, there was about 150,000 pounds of rock ballast up there. Before a single piece of old roofing could come off, all of it had to go.
What is a ballasted roof?
A ballasted roof is a loose-laid system. The membrane and insulation aren't fastened or adhered to the deck. Instead, a layer of stone (or pavers) sits on top and its weight keeps everything in place. Carlisle, one of the big single-ply manufacturers, describes ballast weights from 10 pounds per square foot, the minimum allowed by code, up to 25 pounds or more. The stone also shields the membrane from sun and hail.
Ballasted roofs were popular for decades and you still see plenty of them on stores, schools and offices. The catch comes at replacement time: the stone has to be moved before anyone can see the membrane, let alone replace it. On this job, a couple of our guys spent two days on the roof vacuuming rocks.
How do you reroof a business that stays open?
The short answer is sequencing. Here's how this one ran:
- Days 1 and 2: ballast removal. A small crew vacuumed the rock off the flat section. Quiet, contained, and nothing changes for shoppers.
- Loading day. All the flat-roof material came in. Shingles were staged on the roof. Safety equipment went up and temporary fencing went in around the work area, so customers and staff could get in and out without walking under anything.
- Tear-off day and after. With everything already on the roof and the site fenced, the crew could tear off and dry in fast, section by section.
We planned the job for about four days. Not because the roof needed more time than that, but because the business staying open meant every step had to be planned to keep disruption low.
Need a roof replaced without closing your doors?
Call us and we’ll walk through how the work can be phased around your hours.
What should a building owner ask before a commercial reroof?
- What's actually holding the current roof down? Ballast, fasteners and adhesive each change how tear-off goes, and how long it takes.
- What happens each day? Ask for the sequence: removal, loading, tear-off, dry-in. A roofer who can't describe it hasn't planned it.
- Where will people walk? Entrances, parking, deliveries and drive-throughs all need protecting. Temporary fencing and a clear staging area matter.
- What's the plan for weather? On a flat roof, nothing should be opened up that can't be made watertight the same day.
- Who talks to the store manager? One point of contact keeps surprises off the sales floor.
If your building has a flat roof and you're weighing what goes back on it, Noah's breakdown of tar versus single-ply is a good primer, and our post on parapet walls covers another detail that comes up on commercial roofs.
Who handles commercial work at Hamstra?
The same family company that's been roofing houses since 1978. Our commercial roofing team handles stores, offices, churches and mixed shingle-and-flat buildings like this one, and our multi-family group works with associations and property managers. For access on taller buildings, see how a roof hatch can pay for itself.
Flat roof near the end of its life?
We’ll inspect it, tell you what’s holding it down, and lay out a plan that works around your business.
Questions we hear
Can a store stay open during a roof replacement?
Often, yes. With the work phased (removal, loading, tear-off), temporary fencing around the work area and clear walkways, many businesses stay open throughout. It depends on the building and the roof, so ask your roofer for a day-by-day plan.
What is a ballasted roof?
A ballasted roof is a loose-laid membrane held down by the weight of stone or pavers rather than fasteners or adhesive. Manufacturers describe ballast loads starting around 10 pounds per square foot, the code minimum, and going up from there.
How is roof ballast removed?
On this job, crews vacuumed the rock off the roof over two days before tear-off. Removing ballast first lets the crew see and remove the old membrane.
How long does a commercial reroof take?
It depends on size, roof type and access. This store, with a shingled perimeter and a flat center, was planned for about 4 days so it could stay open.